Which of the following is a disadvantage of the departmental overhead rate method?
A) The departmental overhead rate method assigns overhead on the basis of volume-related measures.
B) The departmental overhead rate method is more refined than the plantwide overhead rate method.
C) The departmental overhead rate method does not assign overhead on the basis of volume- related measures.
D) The departmental overhead rate method is simpler and less costly to implement than the plantwide rate method.
E) There are no disadvantages of the departmental overhead rate method.
A) The departmental overhead rate method assigns overhead on the basis of volume-related measures.
You might also like to view...
Which of the following is an internal user of a company's financial information?
a. Board of directors b. Stockholders in the company c. Holders of the company's bonds d. Creditors with long-term contracts with the company
If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?
A. Check to see which activities cost the least B. Check to see which activities are on the critical path C. Check to see which activities have the longest duration D. Check to see which activities have the highest risk E. Check to see which activities have the most slack
A project with a payback period of four years is acceptable as long as the company's target payback
period is greater than or equal to four years. Indicate whether the statement is true or false
Bonds with the lowest risk of default are often referred to as junk bonds
Indicate whether the statement is true or false