After completing detailed planning for a project, it is often helpful for the project manager and team to apply a sanity test to the project plan. Which of the following accurately describes the application of a sanity test?
a. It is based largely on the expectations of supervisors and sponsors.
b. It is primarily focused on the team members.
c. It should include questions to ensure budgets, schedules and resource plans are reasonable and achievable.
d. It focuses on whether the project charter should be changed
C
You might also like to view...
Connectors tend to seek out marketers who
A) purchase significant amounts of advertising time and space. B) will bribe them. C) act as resources. D) do not follow-up regularly. E) they do not know.
Why do governments and defendants enter into plea bargains?
What will be an ideal response?
Which of the following is an advantage of third-country nationals?
A. Minimizes language and culture problems B. Allows managers to gain international experience C. Compensation is generally easier and is based on local pay scale D. May be less expensive than either parent- or host-country managers E. All of the choice are correct
A corporation reports the following year-end balance sheet data. The company's equity ratio equals: Cash$40,000 Current liabilities$75,000 Accounts receivable 55,000 Long-term liabilities 35,000 Inventory 60,000 Common stock 100,000 Equipment 145,000 Retained earnings 90,000 Total assets$300,000 Total liabilities and equity$300,000
A. 0.63 B. 0.58 C. 2.07 D. 0.37 E. 1.27