Brandon's computer shop has hired a consultant to help apply operations management techniques to increase profits. Currently the shop sells most of its computers to a high-end customized online retailer and sales are steady at 250 per month

A single work cell produces the computers. To produce the computer, three operations are required. First the parts must be assembled, next software must be installed, and finally the computer must be safely packed and labeled for shipping. These operations take 2 hours, 5 hours, and 1 hour respectively. If there are 6 available work hours each day and the shop operates 20 days per month find:
(a) the takt time, and
(b) the number of workers Brandon should hire.


(a) Takt time = (6 hours/day ? 20 days/month)/(250 units/month) = .48 hours per computer (or 28.8 minutes)
(b) Total operation time = 2 + 5 + 1 = 8 hours. Workers required = operation time / takt time = 8/.48 = 16.67 = 17 workers required

Business

You might also like to view...

Saturn is "a different kind of company, different kind of a car;" the Hummer is "like nothing else." These statements indicate a firm's ________

A) product portfolio B) target markets C) positioning D) brand personality E) segmentation

Business

The general price level of goods and services in a nation is steadily increasing. This is known as ______.

A. a negative balance of trade B. deflation C. inflation D. nominal GDP E. a recession

Business

What are some of the myths about nonprofits?

What will be an ideal response?

Business

In the context of consumerism,smart businesses view customer complaints asan opportunity to create better products and stronger relationships.

Answer the following statement true (T) or false (F)

Business