Using LPT priority would result in what sequence for Jobs A, B, C, and D if their process times are 4, 6, 5, and 2 respectively?
A) ABCD
B) DCBA
C) DACB
D) DABC
E) BCAD
E
You might also like to view...
The following UML class diagram should result in how many tables in the relational database?
A. 5 B. 6 C. 7 D. 4
Samuel's average tax rate for 2014 is closest to which of the following?
Samuel Ahn recently graduated from college and started working in a promising career field. He has a little money invested in a stock that pays no dividends. He lives in an apartment, is single, and has no dependents. He has a $22,000 student loan balance and he paid $800 interest in 2014. He is considering going back to school part-time for some additional computer classes. He does not have a personal IRA, and he contributed 2 percent of his $39,500 salary to his employer's 401(k) plan in 2014. As he completes his tax return for 2014, use the information above and below to help him answer the following questions. Standard deduction for 2014: $6,200 Personal exemption for 2014: $3,950 Tax brackets for 2014: Taxable income range Tax rate Up to $9,075 10 percent More than $9,075 but under $36,900 15 percent More than $36,900 but under $89,350 25 percent A) 10% B) 15% C) 12.5% D) 25%
Latoyia Judge is a piece-rate employee at Anible Computers. She receives $30 for each desktop computer that she assembles and has a standard 40 hour work week. During the weekly pay period ending December 15, she completed the assembly of 48 computers and worked 44 hours. What is her gross pay for the pay period?
What will be an ideal response?
How many computer repair troubleshooters should be on duty from 8:00 p.m. to midnight if total demand during that period is 15 calls? The service rate is five (5) calls per hour and the target utilization is 90%
a. Two b. Three c. Four d. Five