What takes place in the Scrum process?

What will be an ideal response?


In Agile PM, Scrum refers to the development strategy agreed to by all key members of the project. Scrum meetings involve assessing the current status of the project, evaluating the results of the previous Sprint, and setting the goals and time-box for the next iteration.
The Scrum process involves a set of meetings that manage the project development process through (1 ) Sprint Planning, (2 ) Daily Scrums, (3 ) the Development Work, (4 ) Sprint Review, and (5 ) Sprint Retrospective. During the Sprint three guidelines shape the process: a) no changes are made that would endanger or modify the sprint goal, b)quality goals to not decrease, and c) scope may be clarified and renegotiated between the project owner and the development team as more is learned.
The work to be performed in the Sprint is identified during the Sprint Planning session. This plan is created by the collaborative work of the entire Scrum team.
The Daily Scrum is a short (15 minutes) event that allows the development team an opportunity to synchronize their activities and create a plan for the next 24-hour time window. During the meeting, members of the development team explain what they accomplished in the past 24 hours to meet the Sprint goal, what they intend to work on during the current day, and identify any problems that might prevent the development team from completing the next Sprint goal.

Business

You might also like to view...

Which one of the following statements is true?

a. External events (transactions) involve interactions between an entity and a party outside the entity. b. Every event or transaction which affects an entity is identified from a source document. c. All economic events can be reliably measured. d. The movement of raw material into production is an external event.

Business

Which of the following accounts might be placed first in a journal entry?

A) Interest Payable, when it has been decreased. B) Accounts Receivable, when it has been decreased. C) Unearned Revenue, when it has been increased. D) Service Revenue, when it has been increased.

Business

Acme, Inc., produces widgets. To manufacture a new type of widget, it took 51 hr for the first widget. Acme estimates it has an 85% learning rate. Using the logarithmic approach, calculate the time it will take to manufacture the 148th widget.

A. 16.24 hr B. 15.86 hr C. 19.52 hr D. 16.94 hr

Business

When the U.S. government announced that no Americans could do business with Iraq, all existing contracts became unenforceable

a. True b. False Indicate whether the statement is true or false