Given the following small project, the critical path is ________ days

Activity Immediate
Predecessor Time
(days)
A - 8
B A 4
C - 10

A) 4
B) 10
C) 12
D) 22
E) None of the above


C

Business

You might also like to view...

A major effort of most businesses, especially retail businesses, in using customer relationship management (CRM) systems is to collect _____ about customers.

A. artificial intelligence B. business intelligence C. personal information D. knowledge management parameters

Business

________ are guides that specify the way certain tasks or activities will be carried out, thereby ensuring uniform action on the part of all corporate members.

Fill in the blank(s) with the appropriate word(s).

Business

Zennia Company provides its employees with varying amount of vacation per year, depending on the length of employment. The estimated amount of the current year's vacation cost is $165,000. The journal entry to record the adjusting entry required on December 31, the end of the current year, to record the current month's accrued vacation pay is

A) $165,000 B) $82,500 C) $0 D) $13,750

Business

The level of the Project Management Maturity Model where the organization applies established project management procedures and techniques is called ________ of project management.

Fill in the blank(s) with the appropriate word(s).

Business