If the standard deviation is 2.78 and the Z value is 1.65, then ______.

a. the expected date of completion is 34.59 weeks if the due date for project completion is 30 weeks
b. the due date for project completion is 34.59 weeks if the expected date of completion is 30 weeks
c. the due date for project completion is 30 weeks if the expected date of completion is 24.51weeks
d. the due date for project completion is 24.51 weeks if the expected date of completion is 30 weeks


b. the due date for project completion is 34.59 weeks if the expected date of completion is 30 weeks

Business

You might also like to view...

A payroll ______________________________ often makes tax and insurance payments for the client

Fill in the blank(s) with correct word

Business

On the issuance date, the Bonds Payable account had a balance of $50,000,000 and Premium on Bonds Payable had a balance of $1,000,000 . What was the issue price of the bonds?

a. $50,000,000 b. $49,000,000 c. $51,000,000 d. Unable to determine from the information given

Business

Abby has been working at her new office job less than a year when she gets pregnant. As she enters the more advanced stages of pregnancy, what can she legally expect in terms of accommodations and guarantees from her employer?

What will be an ideal response?

Business

In the value chain, customer service is concerned with inducing buyers to purchase the product and providing a means for them to do so.

Answer the following statement true (T) or false (F)

Business