Fill in the missing figures below: Units produced 7,900 Standard hours per unit 5 hours Standard hours allowed (a) Standard rate per hour $12.00 Actual hours worked 39,900 Actual labor cost (b) Labor rate variance $5,985 favorable Labor efficiency variance (c)


(a) Standard hours allowed = units produced x standard hours per unit
Standard hours allowed = 7,900 x 5 = 39,500

(b) Labor rate variance = Actual payroll - (Actual hours worked x standard rate)
$5,985 F = Actual payroll - (39,900 x $12.00)
$5,985 F = Actual payroll - $478,800
Actual payroll = $472,815 (favorable variance is deducted from standard)

(c) Labor efficiency variance = (Actual hours - standard hours allowed) x Standard rate
Labor efficiency variance = (39,900 - 39,500 . x $12 = $4,800 U (actual in excess of standard)

Business

You might also like to view...

Answer the following statements true (T) or false (F)

Hypotheses are conclusions derived from the research process.

Business

The resistance points in contract negotiations are determined by:

A. The parties' desired outcomes. B. The parties' target point. C. The parties' BATNAs or MLATNAs. D. The contract zone.

Business

Communication begins when A) an idea is put into words or conveyed through gestures

B) the idea is sent through a communication channel. C) the sender has an idea. D) the receiver decodes the message.

Business

When two or more testators execute the same instrument as their will, the document is called a[n]:

A) Illegal document. B) Reciprocal will. C) Joint will. D) None of the above.

Business