The average tardiness for the job listed in the table below under the longest processing time (LPT) rule is ______.
A. 16 days
B. 14 days
C. 15 days
D. 13 days
C. 15 days
You might also like to view...
Which of the following is most likely to damage the customer-provider relationship?
A. Performing perception checking B. Using a lot of jargon C. Communicating nonverbally D. Using paralanguage
For a profitable company, an increase in the rate of depreciation on a specific project could
a. increase the project's profitability index. b. increase the project's payback period. c. decrease the project's net present value. d. increase the project's internal rate of return.
Admac Technologies has a standard variable overhead rate of $4.50 per machine hour, and each unit produced has a standard time allowed of three hours. The company's static budget was based on 46,000 units. Actual results for the year follow.Actual units produced: 42,000Actual machine hours worked: 120,000Actual variable overhead incurred: $520,000Admac's variable-overhead spending variance is:
A. $27,000 unfavorable. B. $20,000 favorable. C. $20,000 unfavorable. D. $27,000 favorable. E. None of the answers is correct.
The level of risk the organization views as acceptable is the organization's __________
What will be an ideal response?