Answer the following statement(s) true (T) or false (F)
1. The project manager should monitor the progress of any activity with a large time variance even if the expected time does not identify the activity as a critical activity.
2. The variance in the project completion time is the sum of the variances of all activities in the project.
3. The latest finish time for an activity is the largest of the latest start times for all activities that immediately follow the activity
4. The earliest start time for an activity is equal to the smallest of the earliest finish times for all its immediate predecessors.
5. Shortening activity times, which is usually accomplished by adding resources to the project, is called crashing.
1. True
2. True
3. False
4. False
5. True
You might also like to view...
Selective retention works to the advantage of strong brands
Indicate whether the statement is true or false
One aspect of the corporate form can be considered both an advantage and a disadvantage. What aspect is this, and why can it be considered both?
Trade or functional discounts are offered by manufacturers to which of the following?
A) channel intermediaries who perform wholesaling tasks that the manufacturer would otherwise have to perform B) consumers who earn a price reduction for buying in bulk C) intermediaries who pay their bills before they are due D) manufacturers that agree to exclusive distribution contracts E) the government market and other organizations that require bid proposals
A company has already incurred a $55,000 cost in partially producing its three products. Their selling prices when partially and fully processed are shown in the following table with the additional costs necessary to finish their processing. Based on this information, should any products be processed further? ProductUnfinishedSelling Price FinishedSelling Price FurtherProcessing CostsA$72 $108 $35 B 83 124 42 C 94 141 45
A. All of these products should be processed further. B. None of these products should be processed further. C. Products B and C should be processed further. D. Products A and B should be processed further. E. Products A and C should be processed further.