If project completion times are normally distributed, what is the probability that the project will be completed by the mean project duration?

a. 0.00
b. 0.25
c. 0.50
d. 1.00


c. 0.50

Business

You might also like to view...

By producing its ads in France, Revlon obtains effective television commercials at a much higher cost than it would pay for commercials produced in the United States

Indicate whether the statement is true or false

Business

All of the following tests of controls will provide evidence about the physical security of the computer center except

a. review of fire marshal records b. review of the test of the backup power supply c. verification of the second site backup location d. observation of procedures surrounding visitor access to the computer center

Business

______ job design focuses on the job characteristics that affect the psychological meaning and motivational potential of the job, and it views attitudinal variables as the most important outcomes of job design.

A. Biological B. Motivational C. Perceptual-motor D. Organic

Business

During its first year of operations, Silverman Company paid $14,000 for direct materials and $19,000 for production workers' wages. Lease payments and utilities on the production facilities amounted to $17,000 while general, selling, and administrative expenses totaled $8,000. The company produced 5,000 units and sold 3,000 units at a price of $15.00 a unit.What is the amount of finished goods inventory on the balance sheet at year-end?

A. $15,000 B. $20,000 C. $10,000 D. $4,000

Business