What is the early finish time for activity K?

Project Sand Mandala
Carrie meticulously calculated the early and late start and finish times for her latest project and recorded them using different colors of sand on a pristine slab of white marble. She used red for late start and late finish times and green for early start and early finish times. Activity durations and their identifiers were written with black sand. She finished her task and had an opportunity to admire her work only briefly before a colleague came by and swept most of it away. Sadly, this was before Carrie could record the numbers on a more permanent medium, so now she turns to you to help.

Activity Predecessor Duration Early Start Early Finish Late Start Late Finish
A - 10
B - 7 11
C A 7
D A 15 14
E B 11 19
F B 10
G D,E 24
H F 24
J C 28
K G,H,J 36

A) 36
B) 35
C) 34
D) 33


Answer: A

Business

You might also like to view...

The calculation of depletion is similar to the units-of-production depreciation method

Indicate whether the statement is true or false

Business

In order to estimate future demand, companies commonly prepare a company sales forecast first, followed by an industry forecast, and finally a macroeconomic forecast

Indicate whether the statement is true or false

Business

How is conservatism defined from a preparer’s orientation? Which conservatism goal should take precedence when conservatism criteria conflict?

What will be an ideal response?

Business

Developing a product strategy in the Strategic/Consultative Selling Model involves using three prescriptions for successful sales. List each one

What will be an ideal response?

Business