The contractor has subcontracted the cement finishing and shortly after troweling a slab, it begins to rain. Whose responsibility is it to see that the slab is protected?
A. The general contractor
B. The sub-contractor
C. The resident project representative
D. The architect/engineer
E. The inspector
A
You might also like to view...
List and describe four methods of forest reproduction. What are some advantages and disadvantages of each?
What will be an ideal response?
The PMS database has accumulated information regarding the performance of a pavement section before being overlaid as well as the performance of the overlay. The following data were recorded. Develop a linear prediction model (PCR=a + b × Age) for the two cases. If a criterion was established that maintenance or rehabilitation should occur when the PCR reaches a value of 81, when should such actions take place in the two cases?
What will be an ideal response?
The emphasis in NAFTA has been on market integration
Indicate whether the statement is true or false
The condensate drain on a rooftop unit
A) Does not require any type of drain line B) must include a trap unless the unit has an integral trap C) Is normally run through the curb to an inside drain connection D) Does not require a trap because of the short distance