The contractor has subcontracted the cement finishing and shortly after troweling a slab, it begins to rain. Whose responsibility is it to see that the slab is protected?

A. The general contractor
B. The sub-contractor
C. The resident project representative
D. The architect/engineer
E. The inspector


A

Trades & Technology

You might also like to view...

List and describe four methods of forest reproduction. What are some advantages and disadvantages of each?

What will be an ideal response?

Trades & Technology

The PMS database has accumulated information regarding the performance of a pavement section before being overlaid as well as the performance of the overlay. The following data were recorded. Develop a linear prediction model (PCR=a + b × Age) for the two cases. If a criterion was established that maintenance or rehabilitation should occur when the PCR reaches a value of 81, when should such actions take place in the two cases?



What will be an ideal response?

Trades & Technology

The emphasis in NAFTA has been on market integration

Indicate whether the statement is true or false

Trades & Technology

The condensate drain on a rooftop unit

A) Does not require any type of drain line B) must include a trap unless the unit has an integral trap C) Is normally run through the curb to an inside drain connection D) Does not require a trap because of the short distance

Trades & Technology