Explain the four phases of the Rapid Application Development (RAD) methodology. How do they differ from the "traditional" SDLC approach?

What will be an ideal response?


Requirements Planning - Aims at eliciting information and requirements from the senior people and verifying the goals.
Design - The design phase begins once the top-level requirements of the system are identified. To discover more detailed requirements, RAD relies on Joint Application Development (JAD) workshops. If necessary, prototyping is used to verify requirements and invite comments and criticism from users.
Implementation - Once the users approve the preliminary design, a detailed design of the system is created and code is generated. The implementation phase is heavily dependent upon CASE tools and on a series of prototypes that are viewed and reviewed by the key users and that go through a number of iterations by a small but skilled team.
Enhancements and Maintenance - In the framework of RAD, software is never completed until it is retired. Therefore, past the initial stage, all modifications and updates to the software are equal and there is no significant difference between development and maintenance.

Business

You might also like to view...

There is sufficient information on a post-closing trial balance to prepare an income statement

Indicate whether the statement is true or false

Business

Late-mover advantages (or first-mover disadvantages) are not likely to arise when

A. the costs of pioneering are much higher than being a follower and only negligible learning/experience benefits accrue to the pioneer. B. opportunities exist for a blue-ocean strategy to invent a new industry or distinctive market segment that creates altogether new demand. C. technological change is rapid, and fast-following rivals find it easy to leapfrog the pioneer with next-generation products of their own. D. the pioneer's products are somewhat primitive and are easily bested by late movers. E. the marketplace is skeptical about the benefits of a new technology or product being pioneered by a first mover.

Business

The greatest project opportunity occurs when:

A) The project is in the concept phase. B) The project is in the development phase. C) The project is in the implementation phase. D) The project is in the termination phase.

Business

A ________ is a report explaining any differences between the checking account balance according to the depositor's records and the balance reported on the bank statement.

What will be an ideal response?

Business