A PERT project has 45 activities, 19 of which are on the critical path. The estimated time for the critical path is 120 days. The sum of all activity variances is 64, while the sum of variances along the critical path is 36
What is the probability that the project can be completed between days 108 and 120?
A) -2.00
B) 0.0227
C) 0.1058
D) 0.4773
E) 0.9773
D
You might also like to view...
Gary Hamel believes that identifying and challenging debilitating core beliefs that people have about an organization can be helpful in improving management
A. rewards. B. innovation. C. restructuring. D. planning. E. motivation.
The left or debit side of a liability account is used to record ____________________
Fill in the blank(s) with correct word
Universal Services Inc provides communication services to residential and business customers in rural and small urban communities primarily in northern England
The company offers services such as local and long distance voice, data, and Internet and broadband product offerings. The company, in an attempt to increase the attractiveness of its offerings, decides to provide special voice and data packages to its customers. The company designs eight different packs that offer varying voice and data benefits to customers. The company then asks a few of its customers to rank the packs in order to choose two best packs. Which of the following testing methods is being used in this scenario? A) virtual reality testing B) conjoint analysis C) perceptual mapping D) product fabrication E) rapid prototyping
Voir dire is the process whereby the jurors ask prospective judges questions to determine whether they would be biased in their decisions
Indicate whether the statement is true or false