If an activity's optimistic time is four days, its realistic time is 10 days, and its pessimistic time is 25 days, then its estimated time would be 11.5 days

Indicate whether the statement is true or false


TRUE
Explanation: The optimistic time refers to the minimum amount of time that is needed to complete an activity and the pessimistic time refers to the maximum.