An MBA student laboriously calculated the early and late start times and early and late finish times for all of the activities contained in this simple six activity project. Unfortunately, some of the information was washed away by lachrymal fluid

Kindly restore the table to its former glory by filling in the missing information.

Task Predecessor Duration Early Start Early Finish Late Start Late Finish
A -- 8
B A 14
C A 23 8
D C, B 6 23 26
E C 32
F D, E 32 38


Task Predecessor Duration Early Start Early Finish Late Start Late Finish
A -- 8 0 8 0 8
B A 12 8 20 14 26
C A 15 8 23 8 23
D C, B 6 23 29 26 32
E C 9 23 32 23 32
F D, E 6 32 38 32 38

Business

You might also like to view...

The units sold or expected to be sold or sales revenue earned or expected to be earned above the break-even volume is called

A) Margin of safety B) Operating leverage C) Break-even point D) Contribution margin E) Super break-even point

Business

______________ analyze individual performance on all sides.

A. Bi-level evaluations B. Blanchard tests C. 360-degree evaluations D. Omega tests E. Full-view evaluations

Business

Which of the following is an unethical behavior on the part of a consumer?

A. abusing policies about returning goods B. changing price tags in self-service stores C. shoplifting D. being abusive to salespeople E. All these answers are correct.

Business

Activities that take place prior to the point of customization are called upstream activities

Indicate whether the statement is true or false.

Business