A project is composed of 6 activities that have durations and precedence requirements shown in the table. Which of these activities is NOT on the critical path?

Activity Length Predecessor
A 5 --
B 7 A
C 4 A
D 7 B,C
E 7 B
F 6 D, E

A) A
B) B
C) C
D) D


Answer: C

Business

You might also like to view...

To estimate the lifetime value of a customer at a given rate of customer retention, you need to compute the ________

A) net present value of the customer's cash flow B) customer satisfaction index C) future customer value D) customer loyalty index E) gross percent margin of the company

Business

A company provided $12,000 of consulting services on account. The customer promises payment in 30 days. Identify the journal entry below that properly records this transaction.

A.

Accounts Payable12,000 
Consulting Services Revenue 12,000

B.
Accounts Receivable12,000 
Consulting Services Revenue 12,000

C.
Accounts Payable12,000 
Cash 12,000

D.
Consulting Services Revenue12,000 
Cash 12,000

E.
Cash12,000 
Consulting Services Revenue 12,000

Business

Having both Baby Boomers and Millennials in the workplace has sometimes created work-engagement challenges for management. What’s an example of a new corporate trend aimed to mitigate these challenges?

a. early retirement incentives *b. reverse mentorship c. delay the pace of entry for millennials until more boomers retire d. senior mentorship

Business

What are the most beneficial ways to develop a business idea?

a. collect data b. gather feedback c. test the business model d. all of these

Business