The following information is to be used in this and the next question. For the last week a work

center had a planned input of 40 standard hours and an actual input of 36 standard hours.

The
planned output was 40, the actual output 42 standard hours and the beginning backlog was 30
hours. The cumulative input variance was:
A) 0. B) +4. C) -4. D) +2. E) -2.


B

Business

You might also like to view...

Which of the following is LEAST likely a characteristic of a person with a high level of emotional intelligence?

A) self-confidence B) professionalism C) adaptability D) optimism E) empathy

Business

As you amortize the home mortgage, monthly interest payments decline

Indicate whether the statement is true or false.c

Business

The major objective of quality control is to see that the organization produces no imperfect products.

Answer the following statement true (T) or false (F)

Business

Finance is any transaction where money is exchanged for goods and services

Indicate whether the statement is true or false

Business