An activity has a normal duration of 4 hours and a crash time of 4 hours. How much crash time is available for this activity?
a. 4
b. 1
c. 0
d. Cannot be determined from the information given
c. 0
You might also like to view...
When evaluating secondary data, the ________ criteria asks the question of "why the data were collected in the first place."
A) nature B) objective C) error/accuracy D) currency
Just what type of training to offer employees ________.
a. is obvious b. is sometimes difficult to determine c. depends on the service-failure rate d. depends on where in the delivery system the employees are located
Imitation strategies:
A. require expensive and extensive research. B. does not provide organizational legitimacy. C. are rare and inimitable. D. can enhance a firm's performance.
Employees with contracts (bargained collectively or individually) are not at-will employees.
Answer the following statement true (T) or false (F)