In CPM, for activities with more than one immediate predecessor activity, which of the following is used to compute its earliest finish (EF) time

a. largest EF among the immediate predecessors
b. smallest LF among the immediate predecessors
c. smallest EF among the immediate predecessors
d. average of EFs among the immediate predecessors


a

Business

You might also like to view...

The normal activity duration of Activity X is 5 weeks and is budgeted to cost $12,000. The crash time for this activity is 3 weeks and is expected to cost $32,000. The cost slope for Activity X is calculated as ______.

A. (32,000 – 12,000)/(5 – 3) B. (12,000 – 32,000)/(5 – 3) C. (32,000 – 12,000)/(3 – 5) D. (12,000 – 32,000)/(3 – 5)

Business

In a management information system, the data that flow through an organization come from internal company data, competitive intelligence, and market research.

Answer the following statement true (T) or false (F)

Business

When positive reinforcement is employed,

A. negative behavior is likely to be repeated. B. desired behavior is less likely to be repeated. C. same behavior is likely to be repeated. D. undesirable behavior is most likely to occur. E. employee retention is adversely affected.

Business

Which of the following statements about benefits provided by workers compensation programs is true?

A) Occupational disability and nonoccupational disability are covered. B) Death benefits and benefits to eligible survivors are payable if a worker is killed on the job. C) Medical benefits are usually subject to deductibles, coinsurance, and numerous exclusions. D) Retirement benefits are payable to retired workers through workers compensation.

Business