Calculate the latest finish for Task D if one of its successors, Task F, has a latest start on day 9, its other successor, Task E, has a latest start on day 10, and the duration of Task D is 2 days

a. day 9
b. day 10
c. day 12
d. Cannot be calculated based upon information given.


a

Business

You might also like to view...

Which habit is based on the premise that “all things are created twice?”

A. be proactive B. begin with the end in mind C. put first things first D. think win-win

Business

Which of the following is not a member of the Association of South East Asian Nations?

A) Indonesia B) Singapore C) Japan D) Cambodia E) Vietnam

Business

Issues involving ________ are seen as conflicts over limited resources.

A. working conditions B. wages C. benefits D. All of the choices are correct.

Business

If the firm's rate of return on its assets is _____ than the cost of borrowing, then the owners' rate of return on equity will _____ as the firm uses _____ debt.

A. less, decrease, less B. greater, decrease, more C. greater, increase, more D. less, increase, more

Business