In a production process, the total time consumed by all tasks is 45 min. The total time available is 60 min. Given this information, the balance efficiency of the production process is ______.
A. 75%
B. 175%
C. 25%
D. 125%
A. 75%
You might also like to view...
Focus groups can be used to address substantive issues such as deciding on alternative courses of action
Indicate whether the statement is true or false
At the beginning of 20xx, Helms Corporation had 34,000 shares of $10 par value common stock issued and outstanding. During January 20xx, Helms declared and distributed a 10 percent stock dividend. The market value of Helms's stock was $24 throughout the month of January. The entry to be recorded for the declaration of stock dividend is :
a. Stock Dividends 81,600 Common Stock Distributable 34,000 Additional Paid-in Capital 47,600 b. Common Stock Distributable 81,600 Common Stock 81,600 c. Common Stock Distributable 81,600 Common Stock 34,000 Retained Earnings 47,600 d. Stock Dividends 68,000 Cash 68,000
Which activity should be crashed to reduce the project completion by 2 days?
A) Crash activity B by 1 day and Activity C by 1 day. B) Crash activity E by 2 days. C) Crash activity C by 1 day and activity E by 1 day. D) Crash activity B by 2 days.
A team of engineers at General Motors is in charge of discovering new knowledge that can be used to make automobiles safer and more economical. These engineers are conducting
A. basic research. B. research and development. C. applied research. D. product development. E. research and implementation.