If a project is expected to be completed in 68 days with a project variance of 9 days, what is the probability that the project will be completed within 90 days?
a. 85%
b. 90%
c. 95%
d. 100%
d. 100%
You might also like to view...
J. Ross's photography business has assets of $35,000; his investment amounts to $12,000 . Determine the amount of liabilities
a. $47,000 b. None of the answers listed c. $35,000 d. $23,000
A successful business is most likely to view its marketing department as ________
A) the accumulator of customer data B) the link between customers and the business C) the creator of all promotions D) an external shareholder E) a sales-oriented group
The LOHAS and Naturalites segments of the market for environmentally and socially responsible products together represent less than half of the American population
Indicate whether the statement is true or false
An executor or administrator is one who handles a deceased person's estate
Indicate whether the statement is true or false