Drum buffers are:

A) A safety margin separating different projects scheduled to use the same resource.
B) Extra safety that is applied to a project immediately after the use of the constrained resource.
C) A constraint separating different projects that requires a common buffer.
D) Extra safety that is applied to a project immediately before the use of the constrained resource.


D

Business

You might also like to view...

What should an interviewee do once an interview has ended?

a. avoid asking any questions about when he or she may hear from the interviewer b. keep track of the days and follow up with the interviewer if the agreed time has passed c. follow up immediately by calling and sending e-mails to be remembered more easily d. resend his or her cover letter and resume in case the interviewer didn’t keep a copy

Business

Who can be considered “internal customers” of service organizations?

a. Suppliers b. End Users c. Employees d. Potential Customers

Business

The following users of accounting information have an indirect financial interest in the business except

A) regulatory agency. B) creditor. C) taxing authority. D) labor union.

Business

If sales are $400,000, variable costs are 80% of sales, and operating income is $40,000, what is the operating leverage?

A) 0 B) 7.500 C) 2.0 D) 1.333

Business