Given the network shown in Figure 11-1, assume that completion of B is delayed by two days. What happens to the project?

A) The critical path is extended by two days.
B) The start of activity F is delayed by two days.
C) The start of activity E is delayed by two days.
D) All of the above
E) None of the above


D

Business

You might also like to view...

________ is a computer program developed for conducting MDS

A) MONANOVA B) PREFMAP C) LINMAP D) SIMGRAF

Business

Which of the following is NOT one of the six steps that can help smooth the path of customer change?

a. Develop customer trust. b. Understand customers' habits and expectations c. Teach customers to use innovations while limiting trial. d. Pretest new procedures and equipment. e. Publicize the benefits.

Business

Which of the following is an example of a work integration social enterprise?

a. a venture that provides doctors and nurses with better patient data b. a venture that improves the quality of drinking water c. a venture that hires out employees with autism d. a venture that improves access to clean energy

Business

A punctual employee can perform a job under routine circumstances and can act responsibly when the unexpected occurs. _________________________

Answer the following statement true (T) or false (F)

Business