A cost associated with project start-up refers to a(n):

A) recurring cost.
B) one-time cost.
C) incremental cost.
D) infrequent cost.
E) consumable cost.


B
Explanation: B) Costs associated with a project start-up is an example of a one-time cost. These generally include costs associated with project initiation and development and the start-up of the system.
CL

Business

You might also like to view...

The validation method that shows a strong relationship between the score on a test and performance on the job is:

A. Low-level validity B. Criterion-related validity C. Content validity D. High-level validity E. Construct validity

Business

A doctor’s office is considering the purchase of a new piece of equipment. The equipment costs $25,000. The procedure performed with the new equipment will be billed to patients at $200. The doctor’s office estimates that the cost of materials and training for the new equipment will be approximately $75 per procedure. If the doctor’s office estimates that demand for the procedure will be 100 procedures, what should the office do?

a. Purchase the equipment b. Not purchase the equipment c. Impossible to determine d. Cannot be determined from the information given

Business

In order to obtain desired results, one sales training program should be used for everyone so that consistency is promoted among the sales staff.

Answer the following statement true (T) or false (F)

Business

For the purposes of the statute of frauds, an interest in land includes

a. a long-term lease on an apartment. b. a real estate mortgage. c. an easement. d. All of the above.

Business