The sequence of activities that take the longest time from start to finish in a PERT diagram is called the ________ path

A) external
B) lagging
C) minor
D) critical
E) buffered


Answer: D
Explanation: In a PERT network diagram, the sequence of operations that requires the longest time to complete is referred to as the critical path.

Business

You might also like to view...

The dynamic gains from trade include all of the following EXCEPT

a. economies of large-scale production resulting in decreasing unit cost. b. increased saving and investment resulting in economic growth. c. increased competition resulting in lower prices and wider range of output. d. increasing comparative advantage leading to specialization.

Business

Arrow is "a different kind of company, manufacturing a different kind of a car"; the RoadPro is "like nothing else." Statements such as these reflect a firm's ________

A) portfolio B) marketing segment C) positioning D) marketing mix E) mission statement

Business

During the trial phase of Fuel Corporation's suit against Gas Stations, Inc, their attorneys engage in voir dire. This is

a. an assessment of the validity of the arguments for both parties. b. a determination of the issues to be argued before the court. c. the trial. d. the selection of jurors.

Business

In a skateboarding accident with Ryan, Starla is injured. Ryan's insurance company's offers her $25,000 to release him from liability, and she accepts. Later, she learns that her injuries are more serious than she realized. The release

A. bars Starla's further recovery from Ryan. B. is unenforceable because Starla's injuries are unforeseeably difficult. C. is unenforceable because Ryan has a preexisting duty to pay. D. is unenforceable because the release is an illusory promise.

Business