What is the late start time for activity H?
Project Sand Mandala
Carrie meticulously calculated the early and late start and finish times for her latest project and recorded them using different colors of sand on a pristine slab of white marble. She used red for late start and late finish times and green for early start and early finish times. Activity durations and their identifiers were written with black sand. She finished her task and had an opportunity to admire her work only briefly before a colleague came by and swept most of it away. Sadly, this was before Carrie could record the numbers on a more permanent medium, so now she turns to you to help.
Activity Predecessor Duration Early Start Early Finish Late Start Late Finish
A - 10
B - 7 11
C A 7
D A 15 14
E B 11 19
F B 10
G D,E 24
H F 24
J C 28
K G,H,J 36
A) 21
B) 24
C) 17
D) 23
Answer: A
You might also like to view...
Value engineering is?
a. Reducing new product cost by use of readily available parts b. Use of cheaper materials and simpler designs c. Both reducing new product cost by use of readily available parts and use of cheaper materials and simpler designs d. Neither reducing new product cost by use of readily available parts nor use of cheaper materials and simpler designs
Which of the following is not one of the things that managers can do to encourage creativity?
a. Challenging work b. Extrinsic motivation c. Supportive supervision d. Facilitating work skill development
Linear programming is a mathematical programming approach in which at least the objective function or the constraints are assumed to be linear
a. True b. False
Some firms are adopting new software and hardware technologies to get a competitive advantage in personal selling.
Answer the following statement true (T) or false (F)