The project represented by this network diagram has activity lengths in days and crash costs as shown in the table. What is the cheapest crash cost for the project if the contractor must complete all work in 45 days?
Activity Normal Duration Crash Duration Crash Cost/Day
A 10 8 $250
B 16 12 $400
C 12 9 $100
D 17 16 $300
E 14 13 $300
F 6 4 $350
A) $550
B) $950
C) $1150
D) $1450
Answer: C
You might also like to view...
Carla and Eliza share income equally. For the current year, the partnership net income is $40,000 . Carla made withdrawals of $12,000 and Eliza made withdrawals of $21,000 . At the beginning of the year, the capital account balances were: Carla capital, $42,000? Eliza capital, $55,000 . Eliza's capital account balance at the end of the year is
a. $34,000 b. $54,000 c. $78,000 d. $75,000
The Federal Aviation Administration posts monthly percentage on-time arrival data for all the major airlines on its website. Some airlines are regularly on the top of the list, while others are frequently on the bottom of the list. What type of service gap does this list illustrate? What can airlines on the bottom of the list do to address this gap?
What will be an ideal response?
Ben and Ivy enter into a contract under which Ben agrees to cater Ivy's wedding in exchange for a cash down payment. The contract expressly prohibits any transfer of rights. A contract right may be transferred, however, if the transfer involves
A) a right to receive payment B) a right to Ben's services. C) rights under Ivy's insurance policy against Ben's failing to perform. D) a right whose transfer is otherwise expressly prohibited by statute.
In an employment agreement with Karl, Arnold promises to work for Karl for the rest of his life. This promise must be in writing to be enforceable
Indicate whether the statement is true or false