What would be the estimated time for completion if time estimates for programming are as follows? optimistic = 4 weeks; pessimistic = 6 weeks; realistic = 5 weeks

A) 5 weeks
B) 6 weeks
C) 15 weeks
D) 3 weeks
E) 30 weeks


A
Explanation: A) You would use realistic time.

Business

You might also like to view...

There are three different valuation methods: actual, normal, and standard and they can be used with either job order costing or with process costing

Indicate whether the statement is true or false

Business

Which of the following is true of a buyer with an output contract?

A) The buyer cannot sue the seller in case the seller plans to share its output with another buyer. B) The buyer can choose to buy when and what he wants from the seller. C) The buyer is obliged to buy all the goods sold by the seller. D) The buyer cannot enforce the best-efforts clause in the output contract.

Business

Which of these responses is the best answer to the question Where do you see yourself five years from now?

A) I see myself in the position you hold now. B) I prefer to focus on the present. C) I hope to be running my own business. D) As a member of your team, I will have grown and learned enough to advance to a managerial role.

Business

The powers of a corporation are found in

a. the corporation's bylaws. b. the state statutes. c. the corporation's charter. d. all of these.

Business