The less steep the cost slope of an activity, the ________ it costs to shorten one time period.
Fill in the blank(s) with the appropriate word(s).
less
When project managers know an activity's slope, they are able to compare which critical activities to shorten. The less steep the cost slope of an activity, the less it costs to shorten one time period; a steeper slope means it will cost more to shorten one time unit.
You might also like to view...
In U.S. trade law, Section 301, cases involve accusations of
a. international dumping by U.S. companies. b. full-cost pricing by U.S. companies. c. unfair trade practices by foreign nations. d. trade embargoes by foreign nations.
A manufacturer of audio equipment employing an activity-based cost hierarchy uses the unit, batch, product, and facility levels to classify its activities. A batch-level activity is
a. testing products. b. inspection. c. implementation of engineering changes. d. maintenance of the building.
Words such as although, if, because, and since often introduce dependent clauses
Indicate whether the statement is true or false
Yesterday, Lorinda overheard a surprisingly unpleasant encounter between the manager of the hardware store where she works and a sales rep who sells a well-known line of tools. The rep insisted that his tools should be more prominently displayed and that a better assortment would mean more sales. The manager had other plans and told him so, and the conversation turned into a loud argument. What Lorinda observed was an example of
A. a failure of EDI processes. B. passive aggressive behavior. C. sales tactics. D. retail strategy tension. E. channel conflict.