Single-rate methods of preliminary estimating include all of the following EXCEPT ____________.

A. cost per unit
B. cost per unit area
C. cost per typical bay
D. cost per unit volume


Answer: C

Trades & Technology

You might also like to view...

Place the following noncondensing steam turbine startup procedures in order.

____ Verify the lube oil and cooling water are in service. ____ Communicate with the team that the turbine is ready. ____ Open turbine case drains. ____ Slow roll the steam turbine. ____Observe the steam coming out of the drains and, when it becomes dry, completely open the low-pressure steam valve and close the drain valve. ____ Unblock the high-pressure steam. ____ Ensure that the driven equipment connected to the steam turbine is ready for startup. ____ Adjust turbine speed as needed. ____ Open the low-pressure steam valve slightly

Trades & Technology

Policy changes generally are incremental

Indicate whether the statement is true or false

Trades & Technology

The device used to prove that a burner flame is present in a furnace with hot surface ignition is a _____

a. thermocouple b. glow coil c. flame-sensing rod d. bimetal switch

Trades & Technology

The motion of compression and extension, in a shocking absorber, is converted into heat energy and dissipated into the atmosphere.

a. true b. false

Trades & Technology