What is the early start time for activity G?

Project Sand Mandala
Carrie meticulously calculated the early and late start and finish times for her latest project and recorded them using different colors of sand on a pristine slab of white marble. She used red for late start and late finish times and green for early start and early finish times. Activity durations and their identifiers were written with black sand. She finished her task and had an opportunity to admire her work only briefly before a colleague came by and swept most of it away. Sadly, this was before Carrie could record the numbers on a more permanent medium, so now she turns to you to help.

Activity Predecessor Duration Early Start Early Finish Late Start Late Finish
A - 10
B - 7 11
C A 7
D A 15 14
E B 11 19
F B 10
G D,E 24
H F 24
J C 28
K G,H,J 36

A) 11
B) 13
C) 15
D) 19


Answer: C

Business

You might also like to view...

An advertising platform is the

A. basic issue or selling point that an advertiser wishes to include in an advertising campaign. B. objective of the advertising campaign, stated in precise and measurable terms. C. form in which the basic issues of the campaign should be presented. D. broad objectives of the advertising campaign. E. consumer advertising research conducted.

Business

________ is a marketing approach that assumes that the needs satisfied by a product or service and the ways it is used are the same everywhere in the world, and therefore utilizes a common approach in all countries.

A. Nationalized marketing B. Global marketing C. Localized marketing D. Countertrading E. Complementary marketing

Business

A firm requires an investment of $18,000 and will return $25,000 after one year. If the firm borrows $10,000 at 6%, what is the return on levered equity?

A) 80% B) 64% C) 96% D) 112%

Business

The following term refers to an act that creates the greatest good for the greatest number of people:

a. Rights and duties b. Corporate responsibility c. Utilitarianism d. Social sustainability

Business