When it is necessary to reduce project duration and resources are constrained, which of the following is NOT a reasonable option?

A. Critical-chain project management
B. Reduce project scope
C. Compromise quality
D. Establishing a core project team
E. Fast-tracking


Answer: D

Business

You might also like to view...

Sparkling Clean, Inc. is considering implementing a system that will pay its cleaning workers based on the number of completed residential jobs, coupled with satisfactory ratings on random inspections to ensure quality. This system is new to the organization, and it is an example of __________ change.

A. adaptive B. innovative C. familiar D. radically innovative E. highly complex

Business

Cultures with a long-term orientation value:

A. value saving B. thrift C. All options are correct D. future goals E. individual achievement

Business

Certificate-of-title statutes establish perfection requirements for security interest in certain types of goods.

Answer the following statement true (T) or false (F)

Business

The pace of innovation has slowed in the 21st century.

Answer the following statement true (T) or false (F)

Business