What is that sequence of activities that consume the longest amount of time in a project network of activities called?

Fill in the blank(s) with the appropriate word(s).


the critical path

The critical path of activities in a project is the sequence of activities that form the longest chain in terms of their time to complete.

Business

You might also like to view...

Under normal conditions, which of the following would be most likely to increase the coupon rate required to enable a bond to be issued at par?

A. Adding a call provision. B. The rating agencies change the bond's rating from Baa to Aaa. C. Making the bond a first mortgage bond rather than a debenture. D. Adding a sinking fund. E. Adding additional restrictive covenants that limit management's actions.

Business

Which of the following statements is true?

a. The more customers a company has, the better off the company is. b. A company should spare no expense to provide customer satisfaction. c. Most customers make quality determinations by comparing a product or service to a comparable product. d. Cost-benefit analysis can help identify customers that cost more than they are worth to the company.

Business

When conducting selection interviews, Sarah likes to ask questions like “Imagine you are working the night shift and a piece of machinery breaks down. What would you do?” Sarah is asking _______ questions.

A. probing B. unstructured C. closed-ended D. hypothetical E. traditional

Business

The primary advantage of process costing systems is that there is no underapplied or overapplied overhead to account for.

Answer the following statement true (T) or false (F)

Business