A simple sequential project (each task must be completed before the next one can begin) has the time estimates (in days) shown below:



What is the likelihood the project will be completed in 10 days?

 

A. Between 88 and 88 percent

B. Between 89 and 92 percent

C. Between 93 and 97 percent

D. Between 98 and 100 percent


D. Between 98 and 100 percent

Business

You might also like to view...

Describe the Dodd-Frank legislation with regard to credit rating agencies

What will be an ideal response?

Business

Unit-set forms are always single-copy forms

Indicate whether the statement is true or false.

Business

The basic mission of the _____ is topromote global economic cooperation and stable growth.

A. World Bank B. World Trade Organization C. International Monetary Fund D. General Agreement on Tariffs and Trade

Business

Discuss five sources of new-product ideas. What are some techniques could be used to stimulate creative thinking for new-product ideas?

What will be an ideal response?

Business