If the project has a negative cost variance, then
a. no action is needed to be taken, the project is performing well.
b. the project should be watched to be sure the project progresses.
c. more money needs to be expended on the project
d. correction actions should be taken on activities that are near-term and have large estimated costs.
d
You might also like to view...
What are the steps in the scientific method used for organizational behavior?
A. problem statement, review scientific evidence, observations, hypothesis, evaluate and draw conclusions B. problem statement, hypothesis, review scientific evidence, observations, evaluate and draw conclusions C. review scientific evidence, hypothesis, observations, evaluate and draw conclusions, problem statement D. observe, question, develop hypotheses/predictions, collect data, statistically analyze, repeat as needed
A firm can use marketing to attempt to transform a(n) ________ into a perceived need for the firm's product or service
A) brand B) equity C) utility D) want E) demand
Which of the following is the planned-order release using an MRP program if the gross requirement is 670 and the inventory on hand is 600?
A. 70 B. 530 C. 670 D. 600 E. None of these
A proxy statement gives shareholders the right ________
A) of one vote for each share owned B) to give up their vote to another party C) to maintain their proportionate ownership in the corporation when new common stock is issued D) to sell their share of stock at a premium