If the standard deviation is 6.2, the Z value is 2.00, and the expected date of completion is 33 months, then the due date for project completion is ______.

a. 45.40 months
b. 35.75 months
c. 29.65 months
d. 39.55 months


a. 45.40 months

Business

You might also like to view...

Which of the following statements is an advantage of using distribution centers over direct store delivery?

A. Individual stores that forecast and draw from a DC are more cost efficient. B. The DCs enable the retailer to carry less overall inventory. C. The DC can always deliver faster than a vendor. D. The DCs have the advantage of keeping extra merchandise as backup stock in the store. E. Direct store delivery is always more expensive.

Business

Adrienne worked 88 hours during a biweekly period. Her standard workweek comprises 38.5 hours and company policy states that employees may receive overtime or compensatory time for hours worked in excess of 38.5. She has requested compensatory time in lieu of overtime, in keeping with company policy. She must receive ________ hours of compensatory time.

A) 11.5 B) 16.5 C) 15.5 D) 13.5

Business

A chi-squared test of a contingency table with 6 degrees of freedom results in a test statistic of 13.25 . Using the chi-squared table, the most accurate statement that can be made about the p-value for this test is that p-value is greater than .025 but smaller than .05

Indicate whether the statement is true or false

Business

When making the case for an information systems (IS) investment, it is undesirable to translate all potential benefits into monetary terms

Indicate whether the statement is true or false

Business