What is "earned value analysis" as it relates to project scheduling?

What will be an ideal response?


Earned value is a measure of progress. It enables you to assess the “percent of completeness” of a project using quantitative analysis rather than rely on a gut feeling.

Computer Science & Information Technology

You might also like to view...

In C++11 values that persist beyond the statement that created them and have names that make them accessible to other statements in the program are called

a. rvalues b. lvalues c. temporary values d. semantics e. None of these

Computer Science & Information Technology

A(n) ____ shows the relationship of each page to the other pages in the site.

A. flowchart B. index C. wireframe D. data dictionary

Computer Science & Information Technology

You can apply a chart theme to change the overall visual appearance of a chart in terms of its graphic effects, colors, and backgrounds

Indicate whether the statement is true or false

Computer Science & Information Technology

Briefly differentiate between video conferencing and real time video.

What will be an ideal response?

Computer Science & Information Technology