During which of the following phase gates would the questions "Were the project scope objectives met?" and "Were project cost and schedule met?" be answered?

A. Screening and selection
B. Closure
C. Proposal
D. Progress evaluation
E. Implementation


Answer: B

Business

You might also like to view...

What is a BARS system?

What will be an ideal response?

Business

The registration statement must be signed by:

A) the issuer and the chief financial officer. B) the SEC secretary and the chief financial officer. C) the chief financial officer only D) the SEC secretary only.

Business

In Weyerhaeuser v. Ross-Simmons Hardwood Lumber, where Weyerhaeuser was accused of predatory bidding for raw timber to drive out a competitor, the Supreme Court held Weyerhaeuser was:

a. not guilty because predatory bidding does not the violate Robinson-Patman Act, predatory pricing does b. not guilty as there was no evidence it used its bidding power to raise output prices c. guilty as its market share increased to 65 percent, which was evidence of monopolistic impact d. guilty as it raised prices of output after it drove out the competition by buying most of the inputs e. none of the other choices

Business

Establishing evaluation criteria often gives rise to subjectivity issues during the systems development life cycle (SDLC) process

Indicate whether the statement is true or false

Business