A finish to start lag delay is usually shown:
A) As an added value in the predecessor's activity time.
B) On the line adjoining the two activity nodes.
C) As an added value in the predecessors early start time.
D) As a subtracted value in the follower's early finish time.
B
You might also like to view...
Treasurers, Inc., a manufacturer of gift articles, uses a single plantwide rate to allocate indirect costs with machine hours as the allocation base. Estimated overhead costs for the year are $9,000,000. Estimated machine hours are 30,000. During the year, the actual machine hours used were 44,000.
Calculate the predetermined overhead allocation rate. A) $205 B) $153 C) $300 D) $120
Good habits leave a trace, which builds good character over time.
What will be an ideal response?
Lanny Sterling is considering an investment in a solar-powered irrigation system manufacturer. The initial investment is $100,000. He expects to receive cash income of $50,000 a year. What is the payback period?
A) 1 year B) 1.5 years C) 2 years D) 2.5 years E) 3 years
The two basic decisions to be made in developing a compensation plan are the method of payment and
A. career advancement. B. level of compensation. C. number of years of service. D. number of client commendations received. E. designation of the salesperson.