Which of the following is a true statement regarding the personnel roles in a crane lift?

a. The lift director is typically a professional engineer (PE).
b. The crane owner must assume the role of lift director.
c. A single individual can assume more than one role.
d. The signal person must be a certified rigger.


c. A single individual can assume more than one role.

Trades & Technology

You might also like to view...

The following were purposes of Jefferson's Declaration of Independence EXCEPT

A. enlist other British colonies in the Americas to support the cause of American independence. B. ask for an end to slavery throughout America. C. invite assistance from foreign nations. D. explain to the rest of the world why the colonies had revolted. E. rally military, political, and economic resistance to British rule in America.

Trades & Technology

Design a PI controller using root locus techniques for the plant


such that the following performance specifications are met.

System is stable.

What will be an ideal response?

Trades & Technology

Hysteresis loss is often referred to as molecular friction.

Answer the following statement true (T) or false (F)

Trades & Technology

Explain why you would want to fertilize a lake

What will be an ideal response?

Trades & Technology