If the sum of the variances on the critical path (and all other network paths) is equal to zero, what is the probability that the project will be completed by its earliest expected completion date?

A) 50 percent
B) 95 percent
C) 100 percent
D) It cannot be determined.


C

Business

You might also like to view...

If the concept of ethics is so easy to understand, why do ethical dilemmas occur so frequently?

What will be an ideal response?

Business

The process of allocating the historical cost of certain assets to the periods of their use in a reasonably systematic manner is referred to as ____________________

Fill in the blank(s) with correct word

Business

The Universal Service Map is typically ______ and built from the ______ perspective.

a. simple; management b. more complex; guests’ c. more elaborate; employees’ d. basic; guests’

Business

Marketers need to set goals

A) that meet government regulatory approval. B) consistent with the long-term mission and vision of their organizations. C) that are understandable only to employees and investors who read the strategic plan. D) only in the event of a crisis. E) when consumers no longer believe that a firm's products are of the highest quality.

Business