Expected activity completion time can be calculated (where a = optimistic completion time, b = pessimistic completion time, and m = most likely completion time) as:

a. t = (a + m + b)/3
b. t = (2a + 2m + 2b)/6
c. t = (a + 5m + b)/6
d. t = (a + 4m + b)/6


d. t = (a + 4m + b)/6

Business

You might also like to view...

Gains and losses differ from revenues and expenses in that they are produced by ____________________ activities

Fill in the blank(s) with correct word

Business

Employees at Wegners Market began unionizing activities after a series of promotions and job transfers at the firm were handled in a biased manner. They were motivated by

A. dissatisfaction with management. B. economic needs. C. political needs. D. social and status needs.

Business

The decision to pay a cash dividend is within the jurisdiction of ________

A) the SEC B) the board of directors of the firm C) the firm's largest labor union D) the largest shareholders of the firm

Business

The biggest trend in supervisory pay centers on

A. paying a wage that is above that of the highest paid superior. B. payment of higher wages without benefits. C. increased use of variable pay. D. payment of wages that equal subordinate pay.

Business