Using the information in Table J.17 and Johnson's rule, develop a schedule that minimizes makespan for these seven jobs
Assume that job C could be neatly split into two equal parts, each having half of the processing time on each machine as the full job C. Using your original sequence, but splitting job C, what is the makespan for the seven jobs?
A) between 58 and 59 days
B) between 56 and 57 days
C) between 55 and 56 days
D) between 57 and 58 days
D
You might also like to view...
When using XL Data Analyst to compare two mutually exclusive groups as to their respective percentage on a category, the ________ variable is the variable on which the groups will be compared
A) target B) grouping C) independent D) group E) segmenting
Occasion, benefits, usage rate, and customer loyalty are
A) typical behavioral segments. B) event planning tactics. C) four components of the marketing mix. D) measures of internal stakeholder satisfaction. E) elements of newsworthiness.
MoJo Corporation purchases goods on credit terms of 4.5/15, net 40. The cost of non-free trade credit for the 25-day period if the firm did not take discounts but did pay on the due date is:?
A. ?4.5%. B. ?4.71%. C. ?0%. D. ?4.93%. E. ?5.02%.
Data collected over several time periods are
a. time series data b. time controlled data c. crossectional data d. time crossectional data