All of the following are among ground rules that have proven widely useful to project teams EXCEPT:

a. avoid conflict at all costs
b. consider at alternative by considering at least two approaches before proceeding
c. develop trust by doing work as promised and being truthful
d. use data when possible and gather facts rather than arguing over opinions


A

Business

You might also like to view...

The strategic blueprint thinks about how the new product can fit into customers' lives and how it can be distinguished from competitors

Indicate whether the statement is true or false

Business

The 100% rule suggests that before a PERT chart is done, a project manager must:

A. Make sure that each person on the project team got 100% on their project management final exam. B. Make sure 100% of the project tasks are defined. C. Make sure 100% of the project is funded. D. Make sure the project team is devoted solely or 100%, to this project.

Business

Stock dividends have little economic substance for shareholders

Indicate whether the statement is true or false

Business

Only humans can perform an activity in a business process.

Answer the following statement true (T) or false (F)

Business