If each common rafter (including tail) of a gable roof is 14? long, how many 16? pieces of lumber will be needed

to provide common rafters for a 30?-long building with no overhang, constructed on 24? centers?

a. 32
b. 30
c. 28
d. 42


a

Trades & Technology

You might also like to view...

Los acabados de aislamiento:

a. suelen no ser necesarios. b. son fáciles de aplicar. c. siempre se aplican en fábrica. d. se utilizan para impermeabilización

Trades & Technology

The observed biological characteristics brought about by the environment and the genetic code is called the _____________

Fill in the blank(s) with correct word

Trades & Technology

Given the following data, which job(s) will be late if the shortest process time sequencing rule is used?

Today is day 100. Job Process Due Time Date A 4 104 B 1 106 C 5 109 A) B and C will be late. B) A and B will be late. C) A and C will be late. D) All jobs will be on time.

Trades & Technology

Carry the answer to two decimal places. A motor rated at 90 horsepower is actually developing 105 horsepower. What is the percent of horsepower overload?

Fill in the blank(s) with the appropriate word(s).

Trades & Technology