When work is organized into cost control accounts:
A) The work no longer needs to be tracked by the project manager.
B) The subdeliverables become cost centers instead of profit centers for the project.
C) These are assigned to the units performing project activities.
D) These budgets can then be assigned back to the project manager's department.
C
You might also like to view...
Sympathy messages ________
A) must only be sent to people with whom you have a close relationship B) should never be sent in printed cards C) should not be sent until an appropriate amount of time has passed after you hear about the situation D) are more meaningful when handwritten E) will not be appreciated by business acquaintances
Employers have the right to monitor everything from e-mail to Internet use. Give two reasons why an employer would do so and explain each reason
What will be an ideal response?
Memorandum reports and most email reports are directed to:
a. organizational insiders. b. the public stakeholders. c. organizational outsiders. d. internal peers.
Shane Corporation has provided the following data concerning last month's operations. Direct materials$23,000Direct labor$58,000Manufacturing overhead applied to Work in Process$92,000 BeginningEndingWork in process inventory$56,000 $69,000 Finished goods inventory$33,000 $36,000 How much is the unadjusted cost of goods sold on the Schedule of Cost of Goods Sold?
A. $160,000 B. $157,000 C. $193,000 D. $161,000