Identify and briefly describe the three types of project constraints that could impact or change the structure of project network.

Fill in the blank(s) with the appropriate word(s).


Answer will vary

(1) Technical (logic)-the sequence that activities must be performed; (2) Resource-the absence of required people, materials, equipment, or working capital; (3) Physical-limitations based on space or environmental limits.

Business

You might also like to view...

Oreos and Coke are both examples of ________

A) store brands B) cobrands C) private-label brands D) national brands E) ingredient brands

Business

A nonprofit manager measures the organization’s performance by monetizing program costs along with created social value. The manager measures the ______.

A. logic model costs B. social return on investment C. investment made in employee salaries D. financial value of volunteer contributions

Business

The probability that Pete will catch fish when he goes fishing is .88. Pete is going to fish 3 days next week. Define the random variable x to be the number of days Pete catches fish. The probability that Pete will catch fish on one day or less is

A. 0.880. B. 0.038. C. 0.040. D. 0.960.

Business

What are the methods and manners of acceptance as defined by the Uniform Commercial Code (UCC)?

What will be an ideal response?

Business